Supply and installation of LED lighting with electrical installation works
Rest area Nova Gradiška-Dragalić north
The project “Works on the development of the Nova Gradiška–Dragalić North rest area on the A3 Bregana–Zagreb–Lipovac motorway” included the construction of public lighting, including the supply, delivery and installation of LED lamps and lighting poles of various heights (11 m, 12 m and 14 m). The project was implemented in the period from 2021 to 2023, and the investor is Hrvatske autoceste d.o.o.. In addition to the installation of poles and lamps, all necessary electrical installation and electrotechnical works were carried out, including the preparation and installation of materials, ensuring high-quality lighting of the rest area and increased user safety.

2021. – 2023.
Supply, delivery and installation of LED lamps and lighting poles for public lighting and performance of electrical installation works on the project
Hrvatske Autoceste d.o.o.